MTA Board Member on Cuomo’s L-Train Bombshell: It’s Been a ‘Wild’ Ride

And board member David Jones didn't mean in a good way.
MTA Board Member on Cuomo’s L-Train Bombshell: It’s Been a ‘Wild’ Ride
This is what happens when transit is bad. Photo: Lorraine Cink/Twitter

The last thing you want when you’re running a railroad is a “wild” ride.

But that’s exactly what MTA board members got on Thursday when Gov. Cuomo torpedoed a complete 15-month shutdown of the L train tunnel for urgent repairs in favor of a less-intensive, less-comprehensive, untested approach — a move Cuomo made after a brief personal “inspection” of the tunnel and without consulting the board that he claims runs the city’s subway and bus system.

“We didn’t have any warning,” board member David Jones told Streetsblog on Friday. “Suddenly it comes down: there’s a publicity trip to the tunnel and suddenly we’re confronted with a whole new reality. It’s wild.”

“Wild” is not a word Jones said he wanted to ever become affixed to the $477-million L-train shutdown, which has been in the planning process for three years.

“No,” said Jones, an appointee of Mayor de Blasio. “You’re talking about huge amounts of money, more than whole nation’s spend. It’s not inconsequential.”

Jones said he and other board members were “agitated” to be blindsided by the governor, especially with a proposed fix that would not be a complete one.

“I’m not sure if this is a tried-and-true technology,” he said. “The question is: how long is the fix? Are we going to put millions or billions into a fix that will only last a couple of years and leave it to another governor or mayor to rebuild? … I’m concerned. We just have to ask serious questions. We are going to demand [answers]. … It’s not just the mayor’s appointees. Other members of the board are just as agitated. … We’re all sort of shocked.”

Jones’s fellow de Blasio appointee on the board, Veronica Vanterpool, told Streetsblog that she’s more than shocked.

“I’m angered every single day by the quasi-process” she said. “We have a process, but we don’t have meaningful board input and our process is often superseded and circumvented. I always try to balance my anger and frustration with the merits of something. So if they can convince me this is a better alternative, then I want to be supportive of it.”

Jones said he and his fellow board members were never presented with the partial-repair option that Cuomo announced on Thursday.

“We were given just two choices: a total shutdown or one tube while they repair the other,” he said. “We have to know: if this is legitimate, why weren’t we presented with it?”

With David Meyer

Photo of Gersh Kuntzman
Gersh Kuntzman is editor in chief of Streetsblog NYC and Streetsblog USA. He also writes the Cycle of Rage column, which is archived here.

Streetsblog has migrated to a new comment system. New commenters can register directly in the comments section of any article. Returning commenters: your previous comments and display name have been preserved, but you'll need to reclaim your account by clicking "Forgot your password?" on the sign-in form, entering your email, and following the verification link to set a new password — this is required because passwords could not be carried over during the migration. For questions, contact tips@streetsblog.org.

More from Streetsblog Empire State

Tuesday Headlines: Traveling Down The Valley Edition

April 21, 2026

Monday Headlines: Slow March Edition

April 20, 2026

Non Profits, City Officials Put Pressure On Lawmakers To OK Gov. Hochul’s ‘Stop Super Speeders’ Effort

April 20, 2026

‘A Solution, But To What Problem?’ Experts Say AVs Are The Elephant In The Room, But There’s Still Time To Figure Out Their Role

April 20, 2026

Friday Headlines: What About The Buses Edition

April 17, 2026
See all posts